CUTTING
- Cut the pipe right angle to its axis using burr free cutter.
- Ensure that pipes is free from burrs or cutting chip
- Clean the pipe & fitting perfectly before welding.
- Mark welding depth at the end ofpipes.
HEATING
1. Mount the suitable dies on heating element of welding machine accordin to the diameter of Pipe and fitting to be welded.
2. Connect the welding machine to 220/230 volts A.C. power supply.
3. Select 260 Deg. C. temperature on the welding machine thermostat.
4. Wait for reaching the required working temperature.
5. Insert the pipe and the fitting in the dies by exerting light pressure.
6. For heating time, refer the table given for different sizes of Pipes.
WELDING
- After heating, quicklyinsert pipe into the fitting by exerting light pressure.
- Any misalignment should be corrected immediately after insertion to avoid any Stress in the weld.
- Allow the joint to cool as per cooling time given in table.
This type of connection ensures perfect sealing even under the severe working
Conditions. |
 |
 |
 |
|
 |
Recommended Time For PPR Systems Fusion Joints.
PIPE DIA.
(MM) |
WELDING DEPTH
(MM) | HEATING TIME
(SEC) | WELDING TIME
(SEC) |
COOLING TIME
(MIN) |
20 |
14.50 |
6 |
4 |
2 |
25 |
16.00 |
7 |
4 |
2 |
32 |
18.00 |
8 |
6 |
4 |
40 |
20.50 |
12 |
6 |
4 |
50 |
23.50 |
18 |
6 |
4 |
63 |
27.50 |
24 |
8 |
6 |
75 |
30.00 |
30 |
8 |
6 |
90 |
33.00 |
40 |
8 |
6 |
110 |
37.00 |
50 |
10 |
8 |
160 |
55.00 |
60 |
15 |
10 |
|