Jointing Methods : They can be joint by using threaded fittings or plain socket ASTM fittings by using PRINCE Heavy Duty upvc solvent cement. The solvent cement makes pipes & fittings a permanent homogeneous joint and ensures 100% leak-proof plumbing system.
Operating Temperature : The maximum service temperature for PRINCE uPVC- plumbing system is 60°C for continuous flow and 90°C for short time flow.
Installation : Preparing PRINCE uPVC white pipes & fittings for Installation :
Cutting : Cut PRINCE uPVC pipe to the desired length, ensure that the cut pipe & fitting are of compatible sizes. Cut the pipe as squarely as possible for proper bonding.
Debarring / Beveling : Ensure that the cut pipe is free from burrs and filling that might prevent proper contact. Burrs and filling should be removed from outside and inside of the pipe with a suitable file.
Fitting Preparation : Chamfer the end of the pipe to facilitate entry into the fitting. Wipe clean the pipe end & fitting with a dry rag to remove dirt & moisture. If required, use cleaners to clean grease & dirt from pipe & fittings surface to be jointed. Dry fit the pipe to ensure total entry into the bottom of the fittings socket & make a visible marking.
Solvent Cement Application : Use PRINCE Heavy Duty uPVC solvent cement to ensure perfect solvent weld joint. Apply an even coat of solvent cement on both the top of the pipe end & inside thefitting socket. Prince solvent cement eliminates the use of primer up to 2” only, above 2” size, use primer before applying solvent cement.
Assembly : Immediately insert the pipe into the fitting socket. Rotate the pipe ¼ to ½ turn while inserting into the fitting socket. Hold the assembly for approximately 30-60 seconds to avoid push out.
Set & Cure : Assembled joints must be allowed to set & cure properly prior to testingthe system. Set & cure time depends on size, temperature, humidity & pressure. Drying time is faster for drier environment,small size & higher temperature.
|